PROJECT

CATEGORY

Roads

DETAILS

CUSTOMER

Avalon S & C

LOCATION

Lebanese Government represented by the High Relief Committee

START DATA

September 2019

DURATION

1 Months

PROJECT SIZE

Length: 200 m

Project Description

The Project consists of retaining Wall Construction.

The Construction Works include Earthwork, Concrete, steel work, and providing a well-managed drainage system.

Project details

  • Start Date: September 2019 End Date: October 2019
  • Length: 200 m
  • Client: Lebanese Government represented by the High Relief Committee
  • Consultant: Khatib and Alami

Main Works as Considered in the Baseline:

  • Clearing & Grubbing
  • Excavation & Backfill
  • Concrete Work
  • Steel Work
  • Drainage System